Dream Signature, Jogeshwari. How the site team records daily progress in the staff portal, and how management reads it. Version 1 · September 2026.

Contents

1What the Construction section is for

The Construction section replaces the daily WhatsApp report and the paper registers. The site team enters what happened on site each day; management sees it straight away, from anywhere, with progress measured against the contractor's schedule.

It covers three buildings: A-Wing and B-Wing of the Sale Tower (48 slabs each, including OHT/LMR) and the Rehab Tower (37 slabs). The planned dates come from Mandal Infrastructure's tentative schedule dated 29 August 2026.

The site team records

  • A daily progress report (DPR)
  • Each slab's stage, start date and cast date
  • Steel, RMC and other materials received and used
  • Hindrances that hold up work
  • Finishing work, floor by floor

The portal works out

  • How many days each building is ahead or behind
  • Forecast completion dates
  • Manpower, quantities and stock on site
  • Weekly, monthly and custom reports
  • What is due in the next three weeks
The one rule that matters mostThe portal is only as good as what is entered. If a slab is cast and nobody records it, the portal shows the building as behind. Enter everything on the same day.

2Install the app and sign in

Your manager gives you a username and a temporary password. Do not share them: every entry is saved under your name.

Install on your phone (once)

Open portal.dreamindiarealty.com/install on your phone and follow the steps for your phone.

iPhone

  1. Open the link in Safari.
  2. Tap Share (square with an up arrow).
  3. Tap Add to Home Screen, then Add.

Android

  1. Open the link in Chrome.
  2. Tap Install the app, or the ⋮ menu and Install app.

The Dream Signature icon (the red D) appears on your home screen. Open it from there from now on.

First sign-in

  1. Open the app and enter your username and temporary password, then tap Sign in.
  2. Tap your name at the top right, then Change password. Choose a password of at least 8 characters that only you know.
  3. You stay signed in for 30 days on that phone.

3Who can do what

RoleSeesCan add and updateCan delete entries and change planned dates
Site EngineerConstruction onlyYes: DPR, slab stages, materials, hindrances, floor-wise worksNo
Site HeadConstruction onlyYesYes
ManagementAll departmentsYesYes
AdminAll departmentsYesYes, and manages logins

The badge next to your name shows your access: Full access or Can update. Site logins cannot see Sales & CRM, Accounts or Purchase.

4Finding your way around

The dark bar at the top holds the logo, your name (tap it for Change password and Sign out) and the Submit DPR button. Below it are the tabs:

TabWhat it is forMostly used by
OverviewQuick buttons, today's figures, one card per building, schedule chart, 3-week look-ahead, recent activityEveryone
ReportsWeekly, monthly and custom summaries; copy or downloadManagement
Daily reportsSubmit, view and edit DPRs; manpower chartSite team
Slab cycleEvery slab with planned and actual dates, stage and delaySite team
Floor-wise worksFinishing and services progress, floor by floorSite team
MaterialsReceipts, consumption and stock of steel, RMC and othersSite team, stores
HindrancesRegister of anything holding up workSite team

Status labels you will see

LabelMeaning
ScheduledNot started yet, and not due to start yet.
Start not recordedThe planned start date has passed but no start date has been entered. Either work has started (enter the date) or it is genuinely late.
Shuttering Reinforcement …Work is in progress; the label is the current stage.
Overdue · ReinforcementStill in progress after its planned cast date.
CastCast on or before the planned date.
Cast · 5d lateCast, but that many days after the planned date.
On schedule 12 days behindOn a building card: where the forecast finish stands against the planned finish.

5The daily routine

This is what the site team does every working day. It takes about 10 minutes.

WhenWhatWhere
As it happensLog each steel, RMC, cement or block delivery with its challanOverview → Steel / RMC received
As it happensLog anything that stops or slows workOverview → Log hindrance
When a slab changes stageUpdate the stage; on the pour day, enter the cast date, RMC and steelBuilding card → Update dates & stage
End of day, by 7 pmSubmit the DPRSubmit DPR (top right)
Once a weekTick finishing items started or completed on each floorFloor-wise works
One DPR per dayThe Site Head (or the engineer the Site Head names) submits one DPR for the whole site. Other engineers log materials and hindrances as they happen.

6Daily progress report (DPR)

The DPR records who worked on site, what was done, the weather, problems, and tomorrow's plan.

How to submit

  1. Tap Submit DPR at the top right (or Submit today's DPR on the Overview).
  2. Fill in the sections below, from top to bottom.
  3. Tap Submit DPR at the bottom. You see "DPR for … saved" and it appears in Daily reports.

What to enter

FieldWhat to enter
DateToday, filled in for you. Change it only if you are entering a missed day.
ContractorMandal Infrastructure Pvt. Ltd., filled in for you.
WeatherClear, Light rain or Heavy rain — work stopped. Pick heavy rain only if work actually stopped; the reports count these as rain days.
Department labourThe number of workers present on site today in each trade. The usual trades are listed: Carpenter, Steel fixer, Helper / labour, Mason, Welder, Excavator operator. Grey numbers are yesterday's figures as a guide; type today's number over them. Use Add trade for others (e.g. Electrician, Plumber). Leave a trade empty if nobody from it came. The total adds itself up.
Work doneOne line per activity, and for each line choose the building: A-Wing, B-Wing, Rehab Tower, Sale building (A + B) for work across both wings, or Site-wide (e.g. dewatering, labour camp). Use Add work item for more lines.
Slab stage reached todayOptional. For each building's current slab, choose the stage it reached today, or Cast on this date if it was poured. This updates the slab without opening it separately.
Issues / hindrancesAnything that slowed work today, in plain words. If it cost time, also log it in Hindrances (section 9).
SafetyToolbox talk held, PPE issues, any incident or near miss. Write "Nil" if there was nothing.
Plan for tomorrowThe main activities planned for the next day.

Example: a good DPR

Weather: Clear  ·  Labour: Carpenter 93, Steel fixer 36, Helper / labour 28, Mason 1, Excavator operator 2 = 160

Work done

  • Dewatering work — Site-wide
  • Ramp de-shuttering, part 1 — A-Wing
  • Beam bottom and slab shuttering, part 2 — B-Wing
  • Beam and slab steel fixing — Sale building (A + B)
  • Tie-rod hole filling — Rehab Tower

Issues: RMC arrived 2 hours late; pour finished at 9 pm.  ·  Safety: Toolbox talk held. Nil incidents.  ·  Tomorrow: Staircase casting, B-Wing.

Editing a DPR

Open Daily reports, tap the day in the date strip (or use Go to date), then tap Edit. Change what is needed and tap Save changes.

Weak signal on site?The form saves a draft on your phone as you type. If the app closes or the signal drops, open Submit DPR again and your entries come back ("Restored the draft you started at…"). A red bar at the top means you are offline; wait for signal, then tap Submit again.

7Slab cycle: stages and dates

Each slab moves through six stages. Recording them keeps the "days behind" and forecast dates correct.

#StageSelect it when
1ShutteringFormwork for the slab has started. This is the slab's start date.
2ReinforcementSteel fixing for beams and slab has started.
3MEP sleeves & conduitsElectrical conduits, plumbing sleeves and inserts are being placed.
4Pre-pour checksThe slab is being checked before the pour (see the checklist below).
5ConcretingThe pour has started.
6CastThe pour is complete. This is the slab's end (cast) date.

How to update a slab

  1. On the Overview, find the building card and tap Update dates & stage. For any other slab, open Slab cycle, choose the building tab and tap the slab's row.
  2. Start date (actual): the day shuttering began. Entering it moves the slab to Shuttering.
  3. End date / cast date (actual): the day the pour finished. Entering it marks the slab as Cast.
  4. Tap the current stage in the list. Date of this stage defaults to today; change it if the stage was reached earlier.
  5. Holidays in this cycle: working days lost to declared holidays for this slab (the schedule says holidays are added to the cycle). Enter the number of days.
  6. Site note: a short note, e.g. "Reinforcement 70% done, pour planned Friday".
  7. Tap Save update.

Pre-pour checklist

From Pre-pour checks onwards, tick each item when it is done. If a slab is marked Cast with items unticked, the app says how many were missed.

On the pour day

When you select Cast, three more boxes appear. Fill them from the RMC dockets and the steel issue register:

These are added to the Materials register automatically as consumption. Do not enter them again there.

Planned dates (Site Head and Management)

If the contractor issues a revised schedule, open the slab and use Planned dates to change the planned start and end. Leave Move every later slab by the same number of days ticked to shift the rest of the schedule with it, then tap Save planned dates. Site Engineers do not see this box.

Do not change planned dates to hide a delayPlanned dates change only when the contractor formally revises the schedule. Delays are shown by the actual dates.

8Materials: steel, RMC and others

Record every delivery when it arrives, and material used when it is issued. The portal keeps the running totals and stock.

Log a delivery (receipt)

  1. Tap Steel / RMC received on the Overview (or Log receipt on Materials).
  2. Enter the date, pick the material, enter the quantity from the challan.
  3. Enter the grade / spec (e.g. Fe550D 16 mm, M40, OPC 53), the supplier and the challan / docket number.
  4. Choose which building it is for, then tap Log receipt.

Log consumption (material used)

  1. Tap Material used on the Overview (or Log consumption on Materials).
  2. Enter the date, material, and quantity used or issued.
  3. Choose the building and, if it was for a particular slab, the slab.
  4. For steel, enter the Design / BBS qty from the bar bending schedule if you have it; the portal then shows wastage against BBS.
  5. Tap Log consumption.

Units to use

MaterialUnitNote
Reinforcement steelMT (tonnes)Use weighbridge or challan weight. 2,500 kg = 2.5 MT.
RMCm³From each transit mixer docket. Pours are logged through the slab (section 7).
Cementbags50 kg bags.
AAC blocksnosNumber of blocks.
Sand, Aggregatebrass1 brass = 100 cu ft.
Otheras on challanType the material name in Grade / spec.

Reading the Materials tab

9Hindrances

A hindrance is anything outside normal work that stops or slows progress. The register supports delay claims under the contractor's schedule conditions, so record them on the day.

How to log

  1. Tap Log hindrance on the Overview or the Hindrances tab.
  2. Choose the building and the slab affected.
  3. Choose the cause: Materials (RMC, steel, dry materials) · GFC drawings / design decisions · Monsoon / weather · Force majeure · Local disturbances / statutory restrictions · Legal stoppage / permissions · Labour shortage · Site logistics / access · MEP or other agency works · Statutory inspections / approvals · Holiday · Other.
  4. Enter the From date and an estimate of days lost.
  5. Describe what happened in one or two lines, then tap Log hindrance.

Good examples

  • Materials · Rehab Tower · 1st Slab · 1 day lost · "RMC plant breakdown, pour moved from Tue to Wed."
  • GFC drawings · A-Wing · 3rd Slab · 2 days · "Revised beam layout awaited from structural consultant."

When the problem is cleared, open Hindrances and tap Mark resolved.

10Floor-wise works

Tracks finishing and services for every floor: Blockwork, Electrical conduits, Plumbing, Internal plaster, Waterproofing, External plaster, Flooring & tiling, Doors & windows, Painting.

  1. Open Floor-wise works and choose the building.
  2. Find the floor (top floors are at the top) and the activity column.
  3. Tap the cell once for On (work started), again for Done (complete on the whole floor), and a third time to clear it.

Changes save by themselves. The bars at the top show how many floors are done for each activity. The Structure column shows the slab status for that floor.

Only mark Done when the whole floor is finishedPartly finished work stays "On".

11Reading the Overview

How the forecast worksEach slab keeps its planned cycle time (e.g. 10 or 12 days for a typical floor). If a slab starts or finishes late, every later slab moves by the same amount. Entering accurate start and cast dates keeps the forecast honest.

12Reports for management

  1. Open the Reports tab.
  2. Choose the period: This week, Last week, This month, Last month, Project to date or Custom (pick the dates).
  3. Read the summary: DPRs received against days, man-days, slabs cast against planned, steel and RMC, hindrances and rain days.
  4. Below it: progress by building, manpower by day and trade, quantities, hindrances, and every activity carried out.
  5. Copy summary gives a short text to paste into an email or message. Download CSV gives a file that opens in Excel.

Suggested routine: every Monday, review Last week; on the 1st of each month, review Last month.

13Correcting mistakes

MistakeHow to fix itWho
Wrong number or text in a DPRDaily reports → the day → EditSite team
DPR entered for the wrong dateDelete it, then submit it again for the right dateSite Head, Management
Wrong slab stage or dateOpen the slab and correct itSite team
Wrong material entryMaterials → register → Remove, then enter it againSite team
Wrong RMC or steel on a pourOpen the slab, correct the pour quantities, saveSite team
Hindrance logged by mistakeHindrances → DeleteSite Head, Management

Deletions ask for confirmation and cannot be undone.

14Rules for good data

Do

  • Submit the DPR every working day, by 7 pm.
  • Enter the actual date something happened, not the day you remembered it.
  • Count labour from the attendance, not from memory.
  • Copy quantities and challan numbers from the documents.
  • Tag every work line with the right building.
  • Log hindrances on the day they happen.

Don't

  • Share your login or use someone else's.
  • Leave a slab at "Start not recorded" when work has started.
  • Enter pour quantities twice (through the slab and through Materials).
  • Change planned dates without a revised contractor schedule.
  • Keep a problem only in WhatsApp; if it cost time, it goes in Hindrances.

15Problems and answers

I forgot my password.Ask the Admin to reset it from Manage users. You will get a new temporary password.
It says "Incorrect username or password".Check the spelling and that Caps Lock is off. Usernames are lowercase.
I can't see a Delete button or the Planned dates box.Site Engineer logins can't delete or change planned dates. Ask the Site Head.
A red bar says I am offline.Your entries stay in the form. Move to better signal and tap Save or Submit again.
"A DPR for this date already exists".Someone has already submitted today's DPR. Open it from Daily reports and tap Edit to add to it.
A building shows many days behind.Check that the actual start and cast dates are entered for the current and previous slabs. A missing date makes the portal assume the work is late.
The app shows old information.It refreshes every 45 seconds and whenever you come back to it. If in doubt, close the app and open it again.
Something else is wrong.Take a screenshot and send it to the Admin.

16One-page quick reference

I want to…Tap
Submit today's reportSubmit DPR (top right)
Record a slab stage, start or cast dateBuilding card → Update dates & stage
Record a deliveryOverview → Steel / RMC received
Record material usedOverview → Material used
Record a problemOverview → Log hindrance
Mark finishing work on a floorFloor-wise works → tap the cell
See a past DPRDaily reports → tap the day
Get a weekly or monthly summaryReports → choose the period
Change my password or sign outTap your name (top right)
Every day, before you leave siteDPR submitted · slab stages up to date · deliveries logged · hindrances logged.